| Change in per cent | July 2013 | Weight pr cent1 | ||
|---|---|---|---|---|
| June 2013 - July 2013 | July 2012 - July 2013 | |||
| 1The sum of weights for administrative expenses, labour costs and materials deviate from 100 because transport costs are excluded. | ||||
| Plumbing costs total | 0.0 | 1.9 | 186.5 | 100,0 |
| Administrative expenses | -0.2 | 3.5 | 157.6 | 17,3 |
| Labour costs | 0.0 | 2.6 | 165.7 | 26,0 |
| Materials | 0.1 | 1.3 | 205.1 | 55,3 |
| Sanitary installations | 0.1 | 2.5 | 188.4 | 54,5 |
| Materials | 0.1 | 2.3 | 204.9 | 32,7 |
| Heating installations | 0.0 | 1.3 | 184.3 | 45,5 |
| Materials | 0.0 | 0.0 | 205.3 | 22,6 |